Project WIP in Business Central: Choosing and Using a WIP Method

Project WIP diagram: the five WIP methods above contract, usage and invoiced bars, with the WIP gap at period end posting to a G/L entry

Project-based companies, from engineering firms to installers and contract manufacturers, rarely invoice exactly when they incur cost. Without work in process (WIP), the P&L swings from month to month: a big invoice makes one month look great, and the months of labor before it look like losses. Business Central's Projects module (called Jobs in older versions) handles this with WIP methods that defer or accrue cost and revenue until the project's results can be recognized properly.

How project posting works

Usage posted to a project, whether resource time, items or G/L expenses, goes to the P&L as it happens. Invoices billed to the customer go to revenue as they are posted. WIP is a separate, periodic calculation that adjusts those amounts so the P&L reflects how far the project has progressed, and moves the difference to balance sheet WIP accounts.

The five WIP methods

MethodWhat it recognizesTypical fit
Cost ValueRecognizes revenue in proportion to cost incurred, using the expected margin from the budget.Fixed-price projects with reliable cost budgets.
Sales ValueRecognizes cost and revenue based on the sales value of work performed.Projects where the contract value of work done is easy to measure.
Cost of SalesMatches recognized cost to what has been invoiced.Projects billed by milestone where cost should follow billing.
Percentage of CompletionRecognizes revenue and cost based on completion measured against budget.Long-running fixed-price contracts that require percentage-of-completion accounting.
Completed ContractDefers all cost and revenue until the project is complete.Short projects, or where results cannot be estimated reliably.

You can also define your own methods on the Project WIP Methods page by choosing how recognized costs and recognized sales are calculated. The method chosen should follow your revenue recognition policy, so it is a decision for your accountant or auditor as much as for operations.

Set up the project structure first

WIP is only as good as the budget and task structure behind it. Project tasks have a WIP-Total field that decides the level at which WIP is calculated: per task, per group of tasks, or for the whole project. Budget lines (with line type Budget or Both Budget and Billable) provide the expected cost and revenue that methods such as Cost Value and Percentage of Completion rely on. If budgets are missing or unrealistic, recognized revenue will be wrong no matter which method you pick.

The monthly routine

  1. Post all usage and invoices for the period.
  2. Run Calculate WIP for the projects in progress. Review the results on the Project WIP Cockpit or the WIP entries.
  3. Investigate warnings, for example where recognized cost exceeds budget or a project is billed far ahead of progress.
  4. Run Post WIP to G/L. Business Central reverses the previous period's WIP and posts the new amounts.
  5. When a project is complete, set its status to Completed and run Calculate WIP once more so that all WIP is reversed and the final result is recognized.

Fit the WIP run into the wider Business Central month-end close checklist.

Posting groups and accounts

Project posting groups define the WIP and recognition accounts: WIP costs, WIP accrued costs, WIP accrued sales, WIP invoiced sales, and the P&L adjustment accounts. Agree them with finance during design, and make sure the balance sheet WIP accounts are part of your month-end reconciliation.

Dimensions on project entries follow the same rules as everywhere else, see how to design dimensions in Business Central.

Common pitfalls

  • Choosing a method that does not match how the contract is actually priced or billed.
  • Budgets entered once at the start and never revised when scope changes.
  • Projects left open after they finish, so WIP sits on the balance sheet for months.
  • Running WIP for some projects and not others, which makes month-on-month comparisons meaningless.

Project accounting is the focus of our Business Central for project and service businesses work. If your project margins only make sense at year-end, talk to an architect.

ProjectsFinanceBusiness Central

Planning a Business Central project, or worried about one?

Tell us where you are. You'll hear back from an architect within one business day.

Talk to an architectKaspar replies within one business day